Experts say rebuilding Baltimore’s Francis Scott Key Bridge could take anywhere from 18 months to several years
ANNAPOLIS, Md. — Rebuilding Baltimore’s collapsed Francis Scott Key Bridge could take anywhere from 18 months to several years, experts say, while the cost could be at least $400 million — or more than twice that.
It all depends on factors that are still mostly unknown. They range from the design of the new bridge to how swiftly government officials can navigate the bureaucracy of approving permits and awarding contracts.
Realistically, the project could take five to seven years, according to Ben Schafer, an engineering professor at Johns Hopkins University.
“The lead time on air conditioning equipment right now for a home renovation is like 16 months, right?" Schafer said. He continued: “So it’s like you’re telling me they’re going to build a whole bridge in two years? I want it to be true, but I think empirically it doesn’t feel right to me.”
Others are more optimistic about the potential timeline: Sameh Badie, an engineering professor at George Washington University, said the project could take as little as 18 months to two years.
The Key Bridge collapsed Tuesday, killing six members of a crew that was working on the span, after the Dali cargo ship plowed into one its supports. Officials are scrambling to clean up and rebuild after the accident, which has shuttered the city's busy port and a portion of the Baltimore beltway.
The disaster is in some ways similar to the deadly collapse of Florida’s Sunshine Skyway Bridge, which was was struck by a freighter in Tampa Bay in 1980. The new bridge took five years to build, was 19 months late and ran $20 million over budget when it opened in 1987.
But