Subansiri Hydroelectric Project was partially damaged by a landslide, which also impacted the Subansiri River's downstream flow, officials said on Saturday.
A senior NHPC (National Hydroelectric Power Corporation) official said, “One of the five diversion tunnels that was in use, diversion tunnel number 1, was blocked by a landslide on Friday at around 11:30 a.m.”
«After construction was finished, the other four diversion tunnel numbers were already blocked. Consequently, there is a significant decrease in the river flow downstream.
The mean sea level at the dam spillway bay is 145 meters,” the official added.
According to him, the reservoir is holding on to its current 997cum/sec river flow, and its water level is rising. The water level rose to 139 meters at 1:00 p.m.
“By the evening, it is anticipated that the water level would have reached 145 meters, at which point the river will once again flow regularly over the spillway and downstream,» the official mentioned.
The official said, “Since we work in the hills, incidents like these can arise from building activity.
During the years while the building was underway, we also made advantage of the diversion tunnels.”
Lakhimpur District Deputy Commissioner issued an advisory requesting the villagers residing in and around the bank of river Subansiri and adviced them to restrain themselves from activities like fishing, swimming, bathing, plying of boats etc. in the river water and not to venture in the river bed of Subansiri river during night hours under any circumstances to avert any kind of eventualities until return of normaley of the flowing water of the Subansiri river.
“The villagers may also be advised to keep their cattle's like Cow, Goat, Mithun, Pig, Dog