A major nuclear plant that Britain’s government hopes will generate affordable, low-carbon energy could cost up to 46 billion pounds, or $59 billion, and the completion date could be delayed to after 2029
LONDON — A major nuclear plant that Britain's government hopes will generate affordable, low-carbon energy could cost up to 46 billion pounds ($59 billion), and the completion date could be delayed to after 2029, the firm developing it said Wednesday.
The U.K. government says nuclear projects like the Hinkley Point C plant are a key part of its plans to ensure greater energy independence and achieve its “net zero” by 2050 strategy.
But a re-evaluation showed that the final bill for the plant, being built in Somerset in southwest England, could soar to up to 34 billion pounds in 2015 prices — or 43 billion pounds in current value, French energy giant EDF said.
Officials had previously said that the Hinkley plant would start producing electricity in 2027, but the completion date has now been pushed back to 2029 at the earliest.
“Like other infrastructure projects, we have found civil construction slower than we hoped and faced inflation, labor and material shortages — on top of Covid and Brexit disruption," said Stuart Crooks, managing director of Hinkley Point C.
EDF and the U.K. government have said the plant will become a major source of decarbonized electricity supply for the U.K., generating enough to power 6 million homes and providing some 7% of the country's electricity.
The Conservative government is investing heavily in nuclear power, with ambitions to generate up to a quarter of the country's projected electricity demand by 2050.
The move has divided opinion and drawn criticism from green groups.